ACE Santa Clara/Caltrains Station Improvements

Description: Track work refurb and new construction, new turnout, new platform, extend southbound platform, new pedistrian underpass, minor signal work

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94612
 
Senate District
15, 18
Assembly District 09, 10
Congressional District 10, 11
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  6      
Reduced Operating/Maintenance Cost  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MATT TODD (510) 350-2315   MTODD@ACCMA.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$320 $0 $320
Non-bond Funding
State/Federal*
$0 $4,000 $4,000
Local**
$0 $885 $885
 
Total**** $320 $4,885 $5,205

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$320 $4,885 $5,205 $5,205 $5,205 $0
 
Total* $320 $4,885 $5,205 $5,205 $5,205 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2006 

02/28/2009 
 

 
02/01/2006 

02/28/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2006 

12/31/2008 
 

 
10/01/2006 

12/31/2008 
100   

 


Begin Right of Way Phase

End Right of Way Phase
01/01/2009 

04/30/2009 
 

 
01/01/2009 

04/30/2009 
100   

 


Begin Construction Phase

End Construction Phase
12/01/2009 

09/30/2011 
 

 
12/01/2009 

09/30/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2012 

12/31/2012 
08/15/2013 

03/14/2014 
12/01/2013 

02/01/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 6
Reduced Operating/Maintenance Cost 15

Bond Funding Cost
Adopted:
$319,726
Current Approved:
$319,726
Actual Expenditures:
$319,726

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31