Caltrans Logo

Design and Construction of Transit Facility

Description: Design & construction transit maintenance, administration & operations facility. Add'l

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Butte
City Chico, Ca
Zip Code 95928
 
Senate District
04
Assembly District 02, 03
Congressional District 02
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    5  
Reduced Emissions  1    1  
Reduced Operating/Maintenance Cost  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ROBIN VAN VALKENBURGH (530) 879-2468   RVANVALKENBURGH@BCAG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$22 $89 $111
PTMISEA-99313
$6,035 $2,367 $8,403
PTMISEA-99314
$230 $90 $321
Non-bond Funding
State/Federal*
$19,800 $3,087 $22,887
Local**
$10,100 $-6,103 $3,997
 
Total**** $36,188 $-469 $35,719

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$100 $-100 $0 $0 $0 $0
Design(PS&E)
$0 $1,717 $1,717 $3,869 $3,869 $-2,152
Right of Way
$1,800 $0 $1,800 $1,465 $1,465 $335
Construction
$34,288 $-2,086 $32,202 $30,385 $30,385 $1,817
 
Total* $36,188 $-469 $35,719 $35,719 $35,719 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/31/2012 

06/01/2014 
 

 
02/01/2012 

09/01/2013 
90   

 


Begin Right of Way Phase

End Right of Way Phase
03/01/2013 

06/01/2014 
09/27/2016 

09/27/2016 
08/01/2014 

03/01/2016 
100   

 


Begin Construction Phase

End Construction Phase
01/01/2015 

01/01/2016 
09/27/2016 

03/20/2019 
09/01/2014 

01/01/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2016 

06/01/2016 
03/20/2019 

03/20/2019 
03/01/2019 

03/30/2019 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 5
Reduced Emissions 1 1
Reduced Operating/Maintenance Cost 5 5

Bond Funding Cost
Adopted:
$6,287,917
Current Approved:
$8,723,355
Actual Expenditures:
$8,723,355

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31