Caltrans Logo

Replacement Buses for Redwood Coast Transit

Description: Purchase 3 replacement buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Del Norte
City Crescent City
Zip Code 95531
 
Senate District
04
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  25    50  
Reduced Emissions      75  
Reduced Operating/Maintenance Cost      20  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TAMARA LEIGHTON (707) 465-3878   TAMERA@DNITC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $61 $61
PTMISEA-99313
$309 $747 $1,057
Non-bond Funding
State/Federal*
$0 $1,546 $1,546
 
Total**** $309 $2,354 $2,663

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$309 $2,354 $2,663 $2,663 $2,663 $0
 
Total* $309 $2,354 $2,663 $2,663 $2,663 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2011 

06/30/2012 
 

08/11/2023 
10/01/2010 

06/30/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
08/11/2023 

08/11/2023 
07/01/2023 

07/31/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 25 50
Reduced Emissions 75
Reduced Operating/Maintenance Cost 20

Bond Funding Cost
Adopted:
$309,447
Current Approved:
$1,056,947
Actual Expenditures:
$1,056,947

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31