Caltrans Logo

Transit Maintenance and Operations Improvements

Description: Modernization of the transit maintenance and operations facility including new windows, flooring, maint diagnostic scanner, and maint truck.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Benito
City Hollister
Zip Code 95023
 
Senate District
12
Assembly District 28
Congressional District
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10      
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BETTY LIOWEN (831) 637-7665   BETTY@SANBENITOCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $112 $112
PTMISEA-99313
$80 $651 $730
Non-bond Funding
 
Total**** $80 $762 $842

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$80 $762 $842 $99 $99 $742
 
Total* $80 $762 $842 $99 $99 $742

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2013 

04/01/2013 
10/04/2019 

10/04/2019 
09/01/2019 

11/01/2019 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2012 

05/01/2013 
10/04/2019 

04/19/2023 
09/01/2019 

12/01/2023 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2013 

08/01/2013 
03/23/2020 

04/19/2023 
11/01/2019 

12/01/2023 
80   

 


Begin Closeout Phase

End Closeout Phase
09/01/2013 

12/01/2013 
04/19/2023 

04/19/2023 
12/01/2023 

12/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31