Light Rail Vehicle Purchase |
|
Description: Purchasing 29 Light Rail Vehicles
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
San Diego |
| City | San Diego |
| Zip Code | 92101 |
| Senate District |
36, 39, 40 |
| Assembly District | 75, 76, 77, 78, 79 |
| Congressional District | 50, 51, 52, 53 |
| Caltrans District |
11 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Reduced Operating/Maintenance Cost | 5 | 5 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
NANCY DALL | (619) 557-4537 | NANCY.DALL@SDMTS.COM |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $94 | $94 | ||||
| PTMISEA-99313 |
$82,325 | $0 | $82,325 | ||||
| PTMISEA-99314 |
$40,405 | $0 | $40,405 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$0 | $53,941 | $53,941 | ||||
| Local** |
$48,025 | $62,796 | $110,821 | ||||
| Total**** | $170,755 | $116,830 | $287,586 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$170,755 | $116,830 | $287,586 | $287,586 | $287,586 | $0 | |
| Total* | $170,755 | $116,830 | $287,586 | $287,586 | $287,586 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
08/01/2009 10/31/2009 |
02/04/2013 02/04/2013 |
10/05/2009 09/30/2013 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
10/31/2012 03/31/2013 |
04/26/2017 04/26/2017 |
04/01/2017 04/30/2017 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Reduced Operating/Maintenance Cost | 5 | 5 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$122,730,086 |
| Current Approved: |
$122,730,086 |
| Actual Expenditures: |
$122,730,086 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31