                            Description: The sealed corridor program will help reduce the opportunities for accidents at grade crossings within Metrolink corridors.
                             | 
                    
- Project Information
 - Contacts
 - Cost by Fund Source
 - Cost by Component
 - Schedule
 - Map
 
| Project Location | |
|---|---|
| County | 
                                    Los Angeles | 
| City | Los Angeles | 
| Zip Code | 90017 | 
| Senate District | 
                                    18, 19, 20, 21, 22, 23, 24, 25, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38 | 
                                
| Assembly District | 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 48, 49, 50, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80 | 
| Congressional District | |
| Caltrans District | 
                                    07 | 
                                
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase System Reliability | 5 | 5 | 
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA | 
                                    
                                    
                                        
                                            ANNE LOUISE RICE | (213) 452-0211 | RICEA@SCRRA.NET | 
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a  | 
                                    Approved Changes (06/30/2025 b=c-a  | 
                                    Current Approved (06/30/2025 c  | 
                                |||||
| Bond Funding | |||||||
| PTMISEA-99314 | 
                                            $7,280 | $-6,142 | $1,138 | ||||
| Non-bond Funding | |||||||
| State/Federal* | 
                                            $16,040 | $582 | $16,622 | ||||
| Local** | 
                                            $279 | $1,913 | $2,192 | ||||
| Total**** | $23,599 | $-3,646 | $19,953 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a  | 
                                    Approved Changes (06/30/2025 b=c-a  | 
                                    Current Approved (06/30/2025 c  | 
                                    Cost to Date** (06/30/2025 d  | 
                                    
                                        
                                            Cost Forecast (06/30/2025 e  | 
                                            Cost Variance f=c-e  | 
                                        
                                    
                                ||
| Environmental | 
                                        $0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) | 
                                        $779 | $662 | $1,441 | $0 | $0 | $1,441 | |
| Right of Way | 
                                    $0 | $0 | $0 | $46 | $46 | $-46 | |
| Construction | 
                                    $22,820 | $-4,308 | $18,512 | $1,093 | $1,093 | $17,419 | |
| Total* | $23,599 | $-3,646 | $19,953 | $1,138 | $1,138 | $18,814 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a  | 
                                    Approved Changes (mm/dd/yyyy) b  | 
                                    Current Approved (06/30/2025) c  | 
                                    % Complete (06/30/2025) d  | 
                                    Schedule Forecast (06/30/2025) e  | 
                                    Schedule Variance (months) f=c-e  | 
                                
| 
                                        
                                            Begin Environmental Phase
                                             End Environmental Phase  | 
                                      | 
                                      | 
                                      | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Design (PS&E) Phase
                                         End Design (PS&E) Phase  | 
                                    03/01/2009  06/01/2012  | 
                                    09/07/2012  09/09/2014  | 
                                    03/18/2009  08/19/2013  | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Right of Way Phase
                                         End Right of Way Phase  | 
                                      | 
                                    10/09/2015  10/09/2015  | 
                                    10/14/2013  04/18/2014  | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Construction Phase
                                         End Construction Phase  | 
                                    10/01/2012  06/01/2014  | 
                                    09/09/2014  10/09/2015  | 
                                    11/01/2012  12/01/2015  | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Closeout Phase
                                         End Closeout Phase  | 
                                    09/01/2014  12/01/2014  | 
                                    03/06/2017  03/09/2018  | 
                                    05/01/2017  03/30/2018  | 
                                    100 |   | 
                                    0  0  | 
                                
                                ????????
                            
                            
                            
                        No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increase System Reliability | 5 | 5 | 
| Bond Funding Cost | |
|---|---|
| Adopted: | 
                                    $7,279,930 | 
| Current Approved: | 
                                    $1,138,347 | 
| Actual Expenditures: | 
                                    $1,138,347 | 
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31