Caltrans Logo

Regional Transportation Center (Phase 1)

Description: Phase 1 of construction of the RTC that contains regionally significant elements including but not limited to fueling, maintenance, and wash facilities

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05, 14
Assembly District 10, 15, 17, 26
Congressional District 11, 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DONNA DEMARTINO (209) 948-5566   DDMARTINO@SANJOAQUINRTD.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $111 $111
PTMISEA-99313
$11,005 $239 $11,243
PTMISEA-99314
$0 $0 $0
Non-bond Funding
State/Federal*
$0 $17,517 $17,517
 
Total**** $11,005 $17,866 $28,871

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$11,005 $17,866 $28,871 $28,871 $28,871 $0
 
Total* $11,005 $17,866 $28,871 $28,871 $28,871 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2009 

08/01/2011 
 

 
07/01/2009 

08/01/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2012 

05/01/2014 
09/11/2012 

09/11/2012 
06/01/2013 

08/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2014 

08/01/2014 
08/30/2017 

08/30/2017 
12/01/2017 

12/31/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$11,004,573
Current Approved:
$11,243,364
Actual Expenditures:
$11,243,364

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31