Simi Valley Metrolink Station Parking Lot Rehab and ADA Upgrades |
|
Description: Removal of asphalt, replacement of asphalt, landscaping, irrigation upgrades, sidewalk work, striping, and signage.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Ventura |
| City | Ventura |
| Zip Code | 93003 |
| Senate District |
27 |
| Assembly District | 38 |
| Congressional District | |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 5 | 5 |
| Reduced Operating/Maintenance Cost | 10 | 10 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
STEPHANIE YOUNG | (805) 642-1591 X108 | SYOUNG@GOVENTURA.ORG |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $5 | $5 | ||||
| PTMISEA-99313 |
$550 | $-79 | $471 | ||||
| Non-bond Funding | |||||||
| Total**** | $550 | $-73 | $477 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$25 | $-25 | $0 | $11 | $11 | $-11 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$525 | $-48 | $477 | $465 | $465 | $11 | |
| Total* | $550 | $-73 | $477 | $477 | $477 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/14/2013 03/11/2013 |
03/20/2014 03/20/2014 |
09/26/2013 10/07/2013 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/15/2013 11/18/2013 |
03/20/2014 03/24/2015 |
10/14/2013 08/25/2014 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
04/14/2014 06/30/2014 |
03/24/2015 03/24/2015 |
03/09/2015 04/17/2015 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
07/14/2014 08/25/2014 |
07/26/2016 07/26/2016 |
01/05/2016 04/13/2016 |
100 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 5 | 5 |
| Reduced Operating/Maintenance Cost | 10 | 10 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$550,000 |
| Current Approved: |
$471,487 |
| Actual Expenditures: |
$471,487 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31