Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Imperial Transit Park |
Description: Improve safety and security of public transfer passengers by completing a transit transfer terminal.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Imperial |
City | El Centro |
Zip Code | 92243 |
Senate District |
40 |
Assembly District | 80 |
Congressional District | 51 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 25 | 10 |
Increased Ridership | 15 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
KATHI WILLIAMS | (760) 592-4494 | KATHIWILLIAMS@IMPERIALCTC.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$243 | $0 | $243 | ||||
Non-bond Funding | |||||||
State/Federal* |
$974 | $0 | $974 | ||||
Local** |
$0 | $133 | $133 | ||||
Total**** | $1,217 | $133 | $1,350 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$70 | $0 | $70 | $70 | $70 | $0 | |
Design(PS&E) |
$100 | $0 | $100 | $100 | $100 | $0 | |
Right of Way |
$400 | $57 | $457 | $457 | $457 | $0 | |
Construction |
$647 | $77 | $724 | $724 | $724 | $0 | |
Total* | $1,217 | $133 | $1,350 | $1,350 | $1,350 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
09/22/2015 09/22/2015 |
11/01/2015 11/30/2015 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
09/22/2015 09/22/2015 |
11/01/2015 12/01/2015 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
05/12/2016 05/12/2016 |
05/01/2017 05/30/2017 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
11/01/2011 03/31/2012 |
08/16/2018 09/06/2019 |
08/01/2018 06/01/2019 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
03/31/2012 04/30/2012 |
09/06/2019 09/06/2019 |
08/01/2019 09/30/2019 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 25 | 10 |
Increased Ridership | 15 |
Bond Funding Cost | |
---|---|
Adopted: |
$243,000 |
Current Approved: |
$243,000 |
Actual Expenditures: |
$243,000 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31