Imperial Transit Park

Description: Improve safety and security of public transfer passengers by completing a transit transfer terminal.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Imperial
City El Centro
Zip Code 92243
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  25    10  
Increased Ridership  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KATHI WILLIAMS (760) 592-4494   KATHIWILLIAMS@IMPERIALCTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$243 $0 $243
Non-bond Funding
State/Federal*
$974 $0 $974
Local**
$0 $133 $133
 
Total**** $1,217 $133 $1,350

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$70 $0 $70 $70 $70 $0
Design(PS&E)
$100 $0 $100 $100 $100 $0
Right of Way
$400 $57 $457 $457 $457 $0
Construction
$647 $77 $724 $724 $724 $0
 
Total* $1,217 $133 $1,350 $1,350 $1,350 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
09/22/2015 

09/22/2015 
11/01/2015 

11/30/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
09/22/2015 

09/22/2015 
11/01/2015 

12/01/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
05/12/2016 

05/12/2016 
05/01/2017 

05/30/2017 
100   

 


Begin Construction Phase

End Construction Phase
11/01/2011 

03/31/2012 
08/16/2018 

09/06/2019 
08/01/2018 

06/01/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
03/31/2012 

04/30/2012 
09/06/2019 

09/06/2019 
08/01/2019 

09/30/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 25 10
Increased Ridership 15

Bond Funding Cost
Adopted:
$243,000
Current Approved:
$243,000
Actual Expenditures:
$243,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31