Caltrans Logo

Bus Stop Amenities

Description: Purchase and install bust stop signs, schedule holders,shelters, benches and solar units.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City Handford
Zip Code 93232
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20      
Increased Ridership  80      
Reduced Emissions      40  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANGIE DOW (559) 852-2591   ANGIE.DOW@KINGS.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $5 $5
PTMISEA-99313
$118 $400 $518
PTMISEA-99314
$132 $0 $132
Non-bond Funding
 
Total**** $250 $405 $655

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$250 $405 $655 $655 $655 $0
 
Total* $250 $405 $655 $655 $655 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
08/25/2014 

08/25/2014 
06/01/2012 

07/15/2012 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
08/25/2014 

08/25/2014 
08/01/2012 

06/30/2014 
95   

 


Begin Construction Phase

End Construction Phase
07/01/2012 

01/31/2013 
08/25/2014 

03/09/2016 
07/01/2012 

03/01/2016 
90   

 


Begin Closeout Phase

End Closeout Phase
06/01/2013 

06/30/2013 
03/09/2016 

03/09/2016 
06/01/2016 

06/30/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20
Increased Ridership 80
Reduced Emissions 40

Bond Funding Cost
Adopted:
$250,000
Current Approved:
$650,000
Actual Expenditures:
$650,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31