New Transit Facility

Description: Construct a new transit facility for maintenance, operations and administrative functions

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code 93637
 
Senate District
12
Assembly District 31
Congressional District 19
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  2    5  
Reduced Operating/Maintenance Cost      5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RICHARD POYTHRESS (559) 675-0721   RICHARD@MADERACTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$313 $1,193 $1,506
Non-bond Funding
 
Total**** $313 $1,193 $1,506

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $45 $45 $-45
Right of Way
$246 $-246 $0 $0 $0 $0
Construction
$67 $1,439 $1,506 $1,462 $1,462 $45
 
Total* $313 $1,193 $1,506 $1,506 $1,506 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2011 

02/28/2012 
01/27/2015 

01/27/2015 
09/01/2014 

06/01/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
06/01/2010 

03/31/2011 
01/27/2015 

01/27/2015 
07/01/2014 

09/01/2014 
100   

 


Begin Construction Phase

End Construction Phase
07/01/2012 

06/30/2015 
02/26/2020 

02/26/2020 
11/12/2018 

09/30/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2015 

12/31/2015 
03/27/2019 

02/20/2021 
09/30/2019 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 2 5
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$313,234
Current Approved:
$1,506,469
Actual Expenditures:
$1,506,469

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31