Caltrans Logo

Vehicle Procurement

Description: The City of Madera is purchasing two (2) new gasoline Class D 5 passenger van with 2 wheelchair spaces for the ADA/Paratransit service.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code 93637
 
Senate District
14
Assembly District 27
Congressional District 13
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50    50  
Reduced Operating/Maintenance Cost  5    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MARCELA ZUNIGA (559) 661-3692   MZUNIGA@MADERA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $160 $160
Non-bond Funding
 
Total**** $0 $160 $160

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $160 $160 $160 $160 $0
 
Total* $0 $160 $160 $160 $160 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2022 

06/01/2023 
 

09/07/2023 
09/01/2022 

05/31/2023 
 

 


Begin Closeout Phase

End Closeout Phase
06/01/2023 

06/20/2023 
 

09/07/2023 
06/01/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50 50
Reduced Operating/Maintenance Cost 5 10

Bond Funding Cost
Adopted:
$0
Current Approved:
$159,783
Actual Expenditures:
$159,783

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31