Caltrans Logo

Rolling Stock Replacement - (42) Paratransit Vans

Description: (42) paratransit vans, less than 26', gasoline, cut-away chasis type for use in ADA service

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Concord
Zip Code 94520
 
Senate District
07
Assembly District 11
Congressional District 07
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  8      
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANNE MUZZINI (925) 680-2043   MUZZINI@CCCTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$616 $-337 $279
PTMISEA-99314
$482 $-482 $0
Non-bond Funding
State/Federal*
$3,341 $-25 $3,315
Local**
$0 $21 $21
 
Total**** $4,439 $-824 $3,615

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,439 $-824 $3,615 $3,615 $3,615 $0
 
Total* $4,439 $-824 $3,615 $3,615 $3,615 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2010 

09/01/2010 
03/06/2012 

03/06/2012 
01/01/2011 

01/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2011 

03/30/2012 
10/22/2014 

10/22/2014 
08/01/2014 

09/04/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 8
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$1,098,757
Current Approved:
$278,948
Actual Expenditures:
$278,948

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31