Balboa Park Station Improvements Eastside Connections

Description: Upgrades to two Muni Transit light rail stops and construction of accessible path to east entrance of Balboa Park BART station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco
Zip Code 94103
 
Senate District
03, 08
Assembly District 12
Congressional District 08
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOEL GOLDBERG (415) 701-4499   JOEL.GOLDBERG@SFMTA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$593 $186 $779
PTMISEA-99314
$271 $-271 $0
Non-bond Funding
State/Federal*
$0 $660 $660
Local**
$0 $381 $381
 
Total**** $864 $955 $1,819

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$864 $955 $1,819 $1,644 $1,644 $175
 
Total* $864 $955 $1,819 $1,644 $1,644 $175

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2010 

08/31/2010 
 

 
04/01/2010 

08/31/2010 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/31/2010 

03/31/2011 
 

 
08/31/2010 

03/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2011 

12/31/2013 
06/17/2020 

06/17/2020 
12/01/2013 

12/15/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
12/31/2013 

12/31/2014 
06/17/2020 

06/17/2020 
12/16/2017 

12/31/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 1 1

Bond Funding Cost
Adopted:
$863,710
Current Approved:
$778,602
Actual Expenditures:
$778,602

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31