Caltrans Logo

San Bruno Bus Stop Improvements

Description: Replace sidewalks, ADA accessable curb ramps, install 10 solar powered bus shelters with benches, lighting

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Carlos
Zip Code 94070
 
Senate District
12, 19, 21
Assembly District 08, 11
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10    8  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
REBECCA ARTHUR (650) 508-6368   ARTHURR@SAMTRANS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$202 $-66 $136
Non-bond Funding
Local**
$50 $-17 $34
 
Total**** $252 $-82 $170

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$21 $-21 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$231 $-61 $170 $170 $170 $0
 
Total* $252 $-82 $170 $170 $170 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

06/01/2010 
03/05/2012 

03/05/2012 
11/01/2011 

04/30/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/30/2010 

12/31/2010 
03/05/2012 

08/29/2017 
12/01/2011 

06/30/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2011 

02/28/2011 
08/29/2017 

03/05/2019 
07/31/2018 

12/31/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10 8

Bond Funding Cost
Adopted:
$201,600
Current Approved:
$135,781
Actual Expenditures:
$135,781

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31