Caltrans Logo

Daily City Bus Stop Improvements Bayshore Bl

Description: Bus shelter and access improvements at the SamTrans bus stop on Bayshore Bl including extension of sidwalk, construction of accessable curb ramp

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Carlos
Zip Code 94070
 
Senate District
12, 19, 21
Assembly District 08, 11
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    14  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Arthur, Rebecca (650) 508-6368   ARTHURR@SAMTRANS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$187 $-18 $169
Non-bond Funding
Local**
$42 $17 $59
 
Total**** $229 $-1 $228

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$229 $-1 $228 $228 $228 $0
 
Total* $229 $-1 $228 $228 $228 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2010 

07/31/2010 
03/06/2012 

03/06/2012 
11/01/2011 

12/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2010 

09/30/2010 
08/29/2013 

08/29/2013 
09/01/2012 

12/31/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2010 

12/31/2010 
08/29/2013 

08/29/2013 
01/01/2013 

06/30/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 14

Bond Funding Cost
Adopted:
$187,181
Current Approved:
$169,171
Actual Expenditures:
$169,171

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31