Caltrans Logo

Replacement Buses (6)

Description: Purchase six 35' low floor compressed natural gas buses with seating capacity of 32

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Union City
Zip Code 94587
 
Senate District
10
Assembly District 20
Congressional District 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15      
Reduced Emissions  25      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
WILSON LEE (510) 675-5409   WILSONL@UNIONCITY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$90 $0 $90
PTMISEA-99314
$39 $0 $39
Non-bond Funding
State/Federal*
$2,188 $0 $2,188
Local**
$418 $0 $418
 
Total**** $2,736 $0 $2,736

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,736 $0 $2,736 $2,736 $2,736 $0
 
Total* $2,736 $0 $2,736 $2,736 $2,736 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2009 

05/01/2010 
 

 
06/01/2009 

05/01/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2010 

07/01/2010 
 

 
07/01/2010 

07/01/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15
Reduced Emissions 25

Bond Funding Cost
Adopted:
$128,668
Current Approved:
$128,668
Actual Expenditures:
$128,668

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31