Caltrans Logo

Loomis Multi-Modal Park & Ride Lot

Description: Expand & construct 60 parking spaces in the Loomis park & ride lot

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn, Ca
Zip Code 95603
 
Senate District
04
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  15    15  
Reduced Emissions  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVID MELKO (530) 823-4030   DMELK@PCTPA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$23 $0 $23
Non-bond Funding
Local**
$470 $-62 $408
 
Total**** $493 $-62 $431

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$10 $-10 $0 $0 $0 $0
Design(PS&E)
$60 $9 $69 $70 $70 $-1
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$423 $-61 $362 $362 $362 $0
 
Total* $493 $-62 $431 $431 $431 $-1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2010 

05/31/2010 
 

05/08/2012 
04/01/2010 

07/31/2010 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2010 

09/30/2010 
05/08/2012 

05/08/2012 
08/01/2010 

01/01/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2010 

05/31/2011 
05/08/2012 

05/08/2012 
08/01/2011 

12/01/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2011 

07/31/2011 
05/08/2012 

05/08/2012 
02/01/2012 

03/01/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 15 15
Reduced Emissions 5 5

Bond Funding Cost
Adopted:
$22,555
Current Approved:
$22,555
Actual Expenditures:
$22,555

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31