Bus Stop/Facility Improvements-Auburn

Description: Safety improvements include shelter, bench, landscaping, minor road & sidewalk work.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn, Ca
Zip Code 95603
 
Senate District
04
Assembly District 01
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  2    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MEGAN SIREN (530) 823-5211   MSIREN@AUBURN.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$1 $18 $19
PTMISEA-99314
$4 $0 $4
Non-bond Funding
State/Federal*
$0 $11 $11
Local**
$0 $4 $4
 
Total**** $5 $35 $40

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $-0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5 $35 $40 $40 $40 $0
 
Total* $5 $35 $40 $40 $40 $-0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2010 

 
03/16/2012 

 
03/01/2012 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/02/2011 

09/30/2011 
03/05/2019 

03/05/2019 
04/01/2018 

05/01/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
01/02/2012 

03/31/2012 
08/25/2020 

08/25/2020 
04/01/2020 

06/01/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 2 2

Bond Funding Cost
Adopted:
$5,000
Current Approved:
$22,943
Actual Expenditures:
$22,943

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31