Caltrans Logo

CNG Bus Replacement

Description: Purchase of one replacement fixed-route CNG bus.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Blythe
Zip Code 92225
 
Senate District
40
Assembly District 80
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  45    45  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
HELEN COLBERT (760) 921-2340   HCOLBERT@CITYOFBLYTHE.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$123 $-1 $123
PTMISEA-99314
$5 $-5 $0
Non-bond Funding
 
Total**** $129 $-6 $123

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$129 $-6 $123 $123 $123 $0
 
Total* $129 $-6 $123 $123 $123 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2010 

10/01/2010 
04/24/2012 

10/19/2012 
11/01/2011 

10/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2010 

10/31/2010 
02/28/2013 

02/28/2013 
01/01/2013 

06/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 45 45

Bond Funding Cost
Adopted:
$128,604
Current Approved:
$122,674
Actual Expenditures:
$122,674

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31