Operation Facility Modernization & Expansion |
Description: Expansion and modernization of the operations facility to accommodate a larger dispatch center, seperate conference room, computer room, and a reception area for passengers.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside |
City | Riverside |
Zip Code | 92504 |
Senate District |
31 |
Assembly District | 63, 64, 66 |
Congressional District | |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 30 | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
VANESSA JEZIK | (951) 351-6182 | VJEZIK@RIVERSIDECA.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $5 | $5 | ||||
PTMISEA-99313 |
$253 | $100 | $353 | ||||
PTMISEA-99314 |
$13 | $0 | $13 | ||||
Non-bond Funding | |||||||
Total**** | $266 | $105 | $371 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$40 | $0 | $40 | $40 | $40 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$226 | $105 | $331 | $331 | $331 | $0 | |
Total* | $266 | $105 | $371 | $371 | $371 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2010 10/31/2010 |
03/15/2012 03/15/2012 |
01/01/2013 03/31/2013 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2011 07/31/2011 |
08/04/2015 05/23/2016 |
05/08/2015 01/21/2016 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/01/2011 10/31/2011 |
07/09/2019 07/09/2019 |
03/01/2016 10/20/2016 |
75 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 30 | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$266,289 |
Current Approved: |
$366,289 |
Actual Expenditures: |
$366,289 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31