ADA Passenger Accessibility & Loading Improvements

Description: ADA Passenger Accessibility & Loading Improvements

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Shasta
City Redding
Zip Code 96049
 
Senate District
02
Assembly District 04
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ZACH BONNIN (530) 245-7116   ZBONNIN@CI.REDDING.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $5 $5
PTMISEA-99313
$1,849 $-134 $1,715
PTMISEA-99314
$124 $-84 $41
Non-bond Funding
State/Federal*
$0 $3,168 $3,168
Local**
$0 $1,570 $1,570
 
Total**** $1,973 $4,527 $6,500

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$44 $39 $83 $114 $114 $-31
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,929 $4,488 $6,416 $1,646 $1,646 $4,770
 
Total* $1,973 $4,527 $6,500 $1,761 $1,761 $4,739

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/11/2012 

07/11/2012 
11/12/2013 

11/12/2013 
03/01/2013 

08/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2012 

06/01/2013 
11/12/2013 

10/28/2016 
09/01/2013 

03/01/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2013 

12/13/2013 
03/05/2023 

08/22/2022 
03/01/2023 

06/30/2023 
50   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10 1

Bond Funding Cost
Adopted:
$1,972,626
Current Approved:
$1,755,452
Actual Expenditures:
$1,755,452

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31