Caltrans Logo

Bus Facilities Project

Description: Purchase of bus shelters, benches, and display cases for the County of Stanislaus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Modesto
Zip Code 95354
 
Senate District
12
Assembly District 25
Congressional District 18, 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DORALEE BOLES (209) 525-7504   BOLESD@STANCOUNTY.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$40 $0 $40
PTMISEA-99314
$14 $0 $14
Non-bond Funding
 
Total**** $54 $0 $54

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$54 $0 $54 $54 $54 $0
 
Total* $54 $0 $54 $54 $54 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2010 

01/31/2011 
11/27/2012 

11/27/2012 
11/01/2011 

07/31/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2011 

07/31/2011 
11/27/2012 

11/27/2012 
08/01/2012 

08/01/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3

Bond Funding Cost
Adopted:
$53,805
Current Approved:
$53,805
Actual Expenditures:
$53,805

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31