Passenger Information System

Description: Purchase equipments for the passenger info system that includes a Computer Aided Dispatch, Automatic Vehicle Locator System, Automated Passenger Annoucement System and updates to the transit website

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Porterville
Zip Code 93257
 
Senate District
18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  25    25  
Increased Ridership  10      
Reduced Emissions  10      
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RICHARD TREE (559) 782-7448   RTREEMAN@CI.PORTERVILLE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$226 $0 $226
PTMISEA-99314
$17 $0 $17
Non-bond Funding
 
Total**** $243 $1 $244

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$243 $1 $244 $244 $244 $0
 
Total* $243 $1 $244 $244 $244 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/03/2011 

 
 

 
11/03/2011 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/03/2011 

12/05/2011 
 

08/06/2012 
11/03/2011 

02/28/2012 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2011 

06/01/2012 
08/06/2012 

08/06/2012 
06/01/2012 

10/01/2012 
 

 


Begin Closeout Phase

End Closeout Phase
06/01/2012 

07/01/2012 
08/06/2012 

08/06/2012 
12/30/2012 

07/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 25 25
Increased Ridership 10
Reduced Emissions 10
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$243,017
Current Approved:
$243,017
Actual Expenditures:
$243,017

Click to view the Semi-Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31