Caltrans Logo

Los Alamos Bus Stop Improvements

Description: Transit passenger amenities to an existing bus stop including a shelter, bench and trash can.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Santa Barbara
City Santa Barbara
Zip Code 93101
 
Senate District
18
Assembly District 35
Congressional District 24
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MATT DOBBERTEEN (805) 961-8904   MATT@COSBPW,NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$4 $2 $6
PTMISEA-99314
$16 $0 $16
Non-bond Funding
 
Total**** $20 $2 $22

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$20 $2 $22 $20 $20 $2
 
Total* $20 $2 $22 $20 $20 $2

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2015 

03/01/2015 
 

09/21/2016 
02/01/2015 

11/01/2016 
 

 


Begin Closeout Phase

End Closeout Phase
02/01/2015 

05/01/2015 
09/21/2016 

03/13/2017 
11/01/2016 

10/01/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10

Bond Funding Cost
Adopted:
$20,000
Current Approved:
$21,910
Actual Expenditures:
$19,966

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31