Technology Expansion

Description: Working with Cal-ITP. Modernization County Express replace/expand Routematch dispatching workstations, software, upgrade Verizon Mobile Data·Tablets.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Benito
City Hollister
Zip Code 95023
 
Senate District
18
Assembly District 12
Congressional District 17
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5      
Increased Ridership  5      
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
REGINA VALENTINE (831) 637-7665   REGINA@SANBENITOCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $16 $16
PTMISEA-99313
$150 $124 $274
Non-bond Funding
 
Total**** $150 $140 $290

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$150 $140 $290 $159 $159 $131
 
Total* $150 $140 $290 $159 $159 $131

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2016 

04/01/2017 
10/04/2019 

07/10/2023 
08/01/2020 

12/30/2023 
90   

 


Begin Closeout Phase

End Closeout Phase
09/01/2017 

12/01/2017 
04/19/2023 

07/10/2023 
06/30/2023 

12/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Increased Ridership 5
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31