Yard Capital Improvements

Description: Removed a tree in the bus yard. Transferred remaining funds to Technology Expansion project and Transit Maint and Operations Improvement project..

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Benito
City Hollister
Zip Code 95023
 
Senate District
18
Assembly District 12
Congressional District 17
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  5      
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
REGINA VALENTINE (831) 637-7665   REGINA@SANBENITOCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$160 $-160 $0
Non-bond Funding
 
Total**** $160 $-160 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$160 $-160 $0 $0 $0 $-0
 
Total* $160 $-160 $0 $0 $0 $-0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2017 

06/01/2017 
10/04/2019 

04/19/2023 
12/01/2019 

12/01/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2017 

12/01/2017 
04/19/2023 

04/19/2023 
03/01/2023 

03/16/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 5
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$160,000
Current Approved:
$450
Actual Expenditures:
$450

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31