New Passenger Bus Stop Shelter |
Description: Purchase & construct a passenger bus stop shelter in the Native American Community of Hung-A-Lei_Ti in front of the Washoe Tribe's Woodfords Indian Education Center
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alpine |
City | Marklee |
Zip Code | 96120 |
Senate District |
01 |
Assembly District | 05 |
Congressional District | 04 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 1 | 1 |
Increased Ridership | 1 | 1 |
Reduced Emissions | 1 | 1 |
Reduced Operating/Maintenance Cost | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
SCOTT MAAS | (530) 260-0991 | SMAAS@CITILINK.NET |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$12 | $0 | $12 | ||||
Non-bond Funding | |||||||
Total**** | $12 | $0 | $12 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$2 | $0 | $2 | $2 | $2 | $0 | |
Construction |
$10 | $0 | $10 | $10 | $10 | $0 | |
Total* | $12 | $0 | $12 | $12 | $12 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
02/01/2017 04/01/2017 |
04/11/2018 04/11/2018 |
01/19/2018 01/19/2018 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2017 05/01/2017 |
04/11/2018 04/11/2018 |
01/20/2018 02/01/2018 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/01/2017 10/01/2017 |
04/11/2018 04/11/2018 |
02/01/2018 03/23/2018 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
10/01/2017 12/01/2017 |
04/11/2018 04/11/2018 |
03/24/2018 04/03/2018 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 1 | 1 |
Increased Ridership | 1 | 1 |
Reduced Emissions | 1 | 1 |
Reduced Operating/Maintenance Cost | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$15,000 |
Current Approved: |
$11,650 |
Actual Expenditures: |
$11,650 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31