2017 Replace 4 Transit Vehicles

Description: Replace four transit vehicles and ten passenger fareboxes. Three vehicles will be 24 ft light duty buses and one CNG 28 ft light duty bus. Also, purchasing farebox equipment.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City La Mirada
Zip Code 90638
 
Senate District
32
Assembly District 57
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  7    7  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LISA MONTOYA (562) 902-3125   LMONTOYA@CITYOFLAMIRADA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$358 $-28 $330
Non-bond Funding
Local**
$105 $-9 $96
 
Total**** $463 $-37 $426

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$463 $-37 $426 $426 $426 $0
 
Total* $463 $-37 $426 $426 $426 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2018 

07/31/2018 
10/03/2019 

10/03/2019 
05/21/2018 

09/20/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
08/01/2018 

09/30/2018 
10/03/2019 

10/03/2019 
07/15/2019 

09/30/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 7 7

Bond Funding Cost
Adopted:
$357,747
Current Approved:
$329,636
Actual Expenditures:
$329,636

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31