Caltrans Logo

Electric Charging Stations

Description: Procure (10) Electric Charging Stations locating them in Selma, Huron, Kingsburg, Mendota and Kerman

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93721
 
Senate District
14, 16
Assembly District 23, 31
Congressional District 16, 21, 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    10  
Reduced Emissions  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MOSES STITES (559) 233-6789 X244   MSTITES@FRESNOCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$24 $-24 $0
PTMISEA-99313
$720 $3 $723
PTMISEA-99314
$0 $43 $43
Non-bond Funding
 
Total**** $744 $22 $766

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$744 $22 $766 $766 $766 $0
 
Total* $744 $22 $766 $766 $766 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2015 

12/30/2015 
03/09/2016 

03/09/2016 
08/01/2016 

10/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2016 

04/01/2016 
02/20/2020 

02/20/2020 
08/15/2019 

08/29/2019 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 10
Reduced Emissions 10

Bond Funding Cost
Adopted:
$743,811
Current Approved:
$765,950
Actual Expenditures:
$765,950

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31