Caltrans Logo

Replace 3 Wheelchair Lifts on Buses

Description: Replace wheelchair lifts on 3 Dial-A-Ride buses that have exceeded their useful life resulting in high maintenance costs.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Wasco
Zip Code 93280
 
Senate District
16
Assembly District 32
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  8      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SALLY LIVINGSTON (661) 758-7218   SALIVINGSTON@CI.WASCO.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$0 $14 $14
PTMISEA-99314
$0 $0 $0
Non-bond Funding
 
Total**** $0 $14 $14

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $14 $14 $14 $14 $0
 
Total* $0 $14 $14 $14 $14 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
08/13/2015 

03/10/2016 
02/02/2015 

07/09/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
03/10/2016 

03/10/2016 
02/11/2016 

02/23/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 8

Bond Funding Cost
Adopted:
$0
Current Approved:
$14,368
Actual Expenditures:
$14,368

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31