Caltrans Logo

Bus Security Camera System

Description: Design, Purchase and Installation of a Bus Security System

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Gardena
Zip Code 90249
 
Senate District
25
Assembly District 51
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  13    1  
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PAULA FAUST (310) 965-8811   PFAUST@GARDENA.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99314
$150 $0 $150
Non-bond Funding
State/Federal*
$174 $254 $428
Local**
$200 $170 $370
 
Total**** $524 $426 $950

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$79 $-5 $73 $0 $0 $73
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$445 $431 $877 $152 $152 $724
 
Total* $524 $426 $950 $152 $152 $798

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2012 

12/01/2012 
09/11/2012 

09/11/2012 
07/01/2013 

12/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2013 

03/01/2014 
09/02/2014 

09/02/2014 
06/01/2014 

10/01/2014 
90   

 


Begin Closeout Phase

End Closeout Phase
03/01/2014 

06/01/2014 
03/17/2015 

03/17/2015 
04/01/2015 

10/01/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 13 1
Increased Ridership 5

Bond Funding Cost
Adopted:
$150,000
Current Approved:
$150,000
Actual Expenditures:
$150,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31