Description: The sealed corridor program will help reduce the opportunities for accidents at grade crossings within Metrolink corridors.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90017
 
Senate District
18, 19, 20, 21, 22, 23, 24, 25, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38
Assembly District 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 48, 49, 50, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANNE LOUISE RICE (213) 452-0211   RICEA@SCRRA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$7,280 $-6,142 $1,138
Non-bond Funding
State/Federal*
$16,040 $582 $16,622
Local**
$279 $1,913 $2,192
 
Total**** $23,599 $-3,646 $19,953

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$779 $662 $1,441 $0 $0 $1,441
Right of Way
$0 $0 $0 $46 $46 $-46
Construction
$22,820 $-4,308 $18,512 $1,093 $1,093 $17,419
 
Total* $23,599 $-3,646 $19,953 $1,138 $1,138 $18,814

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2009 

06/01/2012 
09/07/2012 

09/09/2014 
03/18/2009 

08/19/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
10/09/2015 

10/09/2015 
10/14/2013 

04/18/2014 
100   

 


Begin Construction Phase

End Construction Phase
10/01/2012 

06/01/2014 
09/09/2014 

10/09/2015 
11/01/2012 

12/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2014 

12/01/2014 
03/06/2017 

03/09/2018 
05/01/2017 

03/30/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 5

Bond Funding Cost
Adopted:
$7,279,930
Current Approved:
$1,138,347
Actual Expenditures:
$1,138,347

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31