Description: The sealed corridor program will help reduce the opportunities for accidents at grade crossings within Metrolink corridors.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | 90017 |
Senate District |
18, 19, 20, 21, 22, 23, 24, 25, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38 |
Assembly District | 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 48, 49, 50, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80 |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
ANNE LOUISE RICE | (213) 452-0211 | RICEA@SCRRA.NET |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99314 |
$7,280 | $-6,142 | $1,138 | ||||
Non-bond Funding | |||||||
State/Federal* |
$16,040 | $582 | $16,622 | ||||
Local** |
$279 | $1,913 | $2,192 | ||||
Total**** | $23,599 | $-3,646 | $19,953 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$779 | $662 | $1,441 | $0 | $0 | $1,441 | |
Right of Way |
$0 | $0 | $0 | $46 | $46 | $-46 | |
Construction |
$22,820 | $-4,308 | $18,512 | $1,093 | $1,093 | $17,419 | |
Total* | $23,599 | $-3,646 | $19,953 | $1,138 | $1,138 | $18,814 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/01/2009 06/01/2012 |
09/07/2012 09/09/2014 |
03/18/2009 08/19/2013 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
10/09/2015 10/09/2015 |
10/14/2013 04/18/2014 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2012 06/01/2014 |
09/09/2014 10/09/2015 |
11/01/2012 12/01/2015 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/01/2014 12/01/2014 |
03/06/2017 03/09/2018 |
05/01/2017 03/30/2018 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$7,279,930 |
Current Approved: |
$1,138,347 |
Actual Expenditures: |
$1,138,347 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31