Bus Procurement

Description: Procurement of (30) 40' Urban Transit buses and (25) 45' Suburban buses. Diesel fueled seating over 30 passengers for local and transbay routes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda, Contra Costa
City Oakland, Ca
Zip Code 94612
 
Senate District
07, 09, 10
Assembly District 09, 11, 14, 16, 18, 20
Congressional District 07, 09, 10, 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15      
Increased Ridership        
Reduced Emissions  11      
Reduced Operating/Maintenance Cost  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KATE MILLER & KIRAN BAWA (510) 891-4859   KMILLER@ACTRANSIT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
SLPP
$16,015 $-6,911 $9,104
PTMISEA-Interest
$0 $24 $24
PTMISEA-99313
$458 $1,277 $1,735
PTMISEA-99314
$43,757 $-6,972 $36,786
Non-bond Funding
State/Federal*
$0 $41,729 $41,729
Local**
$18,801 $-12,077 $6,724
 
Total**** $79,032 $17,070 $96,102

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$79,032 $17,070 $96,102 $96,102 $96,102 $0
 
Total* $79,032 $17,070 $96,102 $96,102 $96,102 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2011 

06/30/2012 
 

08/21/2014 
12/01/2011 

12/31/2014 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2012 

12/31/2013 
 

09/07/2017 
07/01/2012 

07/01/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2015 

06/30/2015 
09/07/2017 

01/17/2019 
07/07/2017 

09/30/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15
Increased Ridership
Reduced Emissions 11
Reduced Operating/Maintenance Cost 20

Bond Funding Cost
Adopted:
$60,230,705
Current Approved:
$38,520,774
Actual Expenditures:
$38,520,774

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31