Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Transit Access Improvement - Meekland |
Description: Construction of curb, gutter and sidewalk, ADA pedestrian ramps, bulbouts and improve street lighting
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda |
City | Oakland |
Zip Code | 94612 |
Senate District |
07, 09, 10 |
Assembly District | 09, 11, 14, 16, 18, 20 |
Congressional District | 07, 09, 10, 13 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 1 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
KATE MILLER & KIRAN BAWA | (510) 891-4859 | KMILLER@ACTRANSIT.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $7 | $7 | ||||
PTMISEA-99313 |
$2,500 | $0 | $2,500 | ||||
Non-bond Funding | |||||||
State/Federal* |
$672 | $-672 | $0 | ||||
Local** |
$0 | $4,167 | $4,167 | ||||
Total**** | $3,172 | $3,502 | $6,674 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$25 | $-25 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $36 | $36 | $36 | $36 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$3,147 | $3,491 | $6,638 | $6,638 | $6,638 | $0 | |
Total* | $3,172 | $3,502 | $6,674 | $6,674 | $6,674 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2011 06/30/2011 |
|
01/01/2011 06/30/2011 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2011 01/01/2012 |
|
01/01/2011 01/01/2012 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2011 11/30/2011 |
|
07/01/2011 11/30/2011 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2012 03/31/2013 |
05/21/2019 05/21/2019 |
06/01/2017 12/31/2018 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
03/31/2013 04/30/2013 |
05/21/2019 05/21/2019 |
12/01/2018 05/01/2019 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,500,000 |
Current Approved: |
$2,500,000 |
Actual Expenditures: |
$2,500,000 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31