Caltrans Logo

Narrow Banding Radio System

Description: Replace entire radio system to meet the 12.5kHz capability requirement

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano
City Dixon
Zip Code 95620
 
Senate District
05
Assembly District 08
Congressional District 10
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10      
Increased Ridership  2      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LIZ NIEDZIELA (707) 399-3217   ENIEDZIELA@STA-SNCI.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99314
$21 $-4 $17
Non-bond Funding
State/Federal*
$3 $-3 $0
 
Total**** $24 $-7 $17

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$24 $-7 $17 $17 $17 $0
 
Total* $24 $-7 $17 $17 $17 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
90   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2011 

11/30/2011 
08/16/2012 

08/16/2012 
09/01/2012 

10/31/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2012 

06/30/2012 
11/08/2013 

11/08/2013 
10/31/2013 

11/15/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10
Increased Ridership 2

Bond Funding Cost
Adopted:
$21,223
Current Approved:
$17,249
Actual Expenditures:
$17,249

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31