Yuba-Sutter Transit Commuter Buses

Description: Purchase three new inner-city commuter buses - rolling stock replacement & expansion

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sutter, Yuba
City Sacramento
Zip Code 95814
 
Senate District
04
Assembly District 02, 03
Congressional District 02
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GARY TAYLOR (916) 340-6279   GTAYLOR@SACOC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$650 $0 $650
PTMISEA-99314
$45 $0 $45
Non-bond Funding
State/Federal*
$955 $86 $1,041
 
Total**** $1,650 $86 $1,736

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,650 $86 $1,736 $1,736 $1,736 $0
 
Total* $1,650 $86 $1,736 $1,736 $1,736 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2011 

11/30/2011 
08/16/2012 

08/16/2012 
04/19/2012 

10/31/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2011 

12/31/2011 
08/16/2012 

08/16/2012 
12/01/2012 

12/31/2012 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10

Bond Funding Cost
Adopted:
$695,000
Current Approved:
$695,000
Actual Expenditures:
$695,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31