SRTD South Line Phase II - CRC Parking Facility |
Description: Construct Parking Structure at the terminus of the So. Sac Corridor - Phase II Light Rail Ext. @ Cosumnes River College
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento |
City | Sacramento |
Zip Code | 95814 |
Senate District |
06 |
Assembly District | 07 |
Congressional District | 05 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 6 | 6 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
CHRISTINE O'ROURKE | (916) 340-6262 | COROURKE@SACOG.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$4,307 | $-4,307 | $0 | ||||
SLPP |
$7,200 | $0 | $7,200 | ||||
PTMISEA-99313 |
$17,537 | $-1,813 | $15,724 | ||||
Non-bond Funding | |||||||
State/Federal* |
$188,803 | $-188,803 | $0 | ||||
Local** |
$39,928 | $-27,222 | $12,706 | ||||
Total**** | $257,775 | $-222,146 | $35,630 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$27,003 | $-27,003 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$10,269 | $-10,269 | $0 | $0 | $0 | $0 | |
Right of Way |
$4,098 | $-4,098 | $0 | $0 | $0 | $0 | |
Construction |
$216,405 | $-180,776 | $35,630 | $35,630 | $35,630 | $0 | |
Total* | $257,775 | $-222,146 | $35,630 | $35,630 | $35,630 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
11/01/2011 06/30/2013 |
04/06/2015 |
11/01/2011 05/01/2015 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/01/2013 02/28/2014 |
04/06/2015 04/06/2015 |
06/01/2015 06/30/2015 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 6 | 6 |
Bond Funding Cost | |
---|---|
Adopted: |
$29,044,331 |
Current Approved: |
$15,724,138 |
Actual Expenditures: |
$15,724,138 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31