Caltrans Logo

SRTD South Line Phase II - CRC Parking Facility

Description: Construct Parking Structure at the terminus of the So. Sac Corridor - Phase II Light Rail Ext. @ Cosumnes River College

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code 95814
 
Senate District
06
Assembly District 07
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  6    6  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CHRISTINE O'ROURKE (916) 340-6262   COROURKE@SACOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
RIP Augmentation
$4,307 $-4,307 $0
SLPP
$7,200 $0 $7,200
PTMISEA-99313
$17,537 $-1,813 $15,724
Non-bond Funding
State/Federal*
$188,803 $-188,803 $0
Local**
$39,928 $-27,222 $12,706
 
Total**** $257,775 $-222,146 $35,630

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$27,003 $-27,003 $0 $0 $0 $0
Design(PS&E)
$10,269 $-10,269 $0 $0 $0 $0
Right of Way
$4,098 $-4,098 $0 $0 $0 $0
Construction
$216,405 $-180,776 $35,630 $35,630 $35,630 $0
 
Total* $257,775 $-222,146 $35,630 $35,630 $35,630 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2011 

06/30/2013 
 

04/06/2015 
11/01/2011 

05/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2013 

02/28/2014 
04/06/2015 

04/06/2015 
06/01/2015 

06/30/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 6 6

Bond Funding Cost
Adopted:
$29,044,331
Current Approved:
$15,724,138
Actual Expenditures:
$15,724,138

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31