Altamont Rail Corridor (Positive Train Control)

Description: Track, positve train control, and signaling along the existing and planned Altamont Commuter Express operational corridors

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
15, 18
Assembly District 09, 10
Congressional District 10, 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50      
Reduced Emissions  10      
Reduced Operating/Maintenance Cost  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GEORGE FINK (209) 944-6235   GEORGE@ACERAIL.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $41 $41
PTMISEA-99314
$2,088 $382 $2,470
Non-bond Funding
State/Federal*
$12,833 $-5,638 $7,195
Local**
$1,100 $-621 $479
 
Total**** $16,021 $-5,836 $10,184

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$16,066 $-5,881 $10,184 $8,929 $8,929 $1,255
 
Total* $16,021 $-5,836 $10,184 $8,929 $8,929 $1,255

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2010 

08/31/2010 
 

 
04/01/2010 

08/31/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2011 

06/30/2016 
10/04/2017 

08/15/2018 
09/30/2017 

12/31/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2016 

09/30/2016 
03/01/2019 

03/01/2019 
01/31/2020 

03/31/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50
Reduced Emissions 10
Reduced Operating/Maintenance Cost 15

Bond Funding Cost
Adopted:
$2,087,516
Current Approved:
$2,470,012
Actual Expenditures:
$2,470,012

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31