Caltrans Logo

Bus & Bus Facilities/Passenger Amenities

Description: Construction of shelters and passenger amenities at bus stops for the BRT along Hammer Lane

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05, 14
Assembly District 10, 15, 17, 26
Congressional District 11, 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DONNA DEMARTINO (209) 948-5566   DDEMARTINO@SANJOAQUINRTD.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $37 $37
PTMISEA-99314
$2,800 $184 $2,984
Non-bond Funding
 
Total**** $2,800 $221 $3,021

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$133 $0 $133 $133 $133 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,667 $221 $2,888 $2,888 $2,888 $0
 
Total* $2,800 $221 $3,021 $3,021 $3,021 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2011 

07/01/2011 
 

 
05/01/2011 

07/01/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2011 

12/01/2011 
 

 
07/01/2011 

12/01/2011 
 

 


Begin Right of Way Phase

End Right of Way Phase
02/01/2012 

04/01/2012 
 

 
02/01/2012 

04/01/2012 
 

 


Begin Construction Phase

End Construction Phase
05/01/2012 

12/01/2012 
 

09/11/2012 
05/01/2012 

12/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2013 

08/01/2013 
08/22/2019 

08/22/2019 
07/01/2019 

10/31/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5

Bond Funding Cost
Adopted:
$2,799,774
Current Approved:
$2,983,843
Actual Expenditures:
$2,983,843

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31