Grover Beach Station Expansion

Description: Expand the existing train station to include a new bus drop off location and shelter, additional parking, and bike lockers.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo
City San Luis Obispo
Zip Code 93401
 
Senate District
15
Assembly District 33
Congressional District
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3    0  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PETER RODGERS (805) 781-5712   PRODGERS@SLOCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $29 $29
PTMISEA-99313
$1,000 $-215 $785
Non-bond Funding
State/Federal*
$0 $2,310 $2,310
Local**
$160 $-4 $156
 
Total**** $1,160 $2,120 $3,280

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$50 $-50 $0 $0 $0 $0
Design(PS&E)
$110 $-53 $57 $57 $57 $0
Right of Way
$0 $320 $320 $320 $320 $0
Construction
$1,000 $1,903 $2,903 $2,903 $2,903 $0
 
Total* $1,160 $2,120 $3,280 $3,280 $3,280 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2009 

08/01/2011 
 

02/16/2016 
09/01/2009 

01/01/2016 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2011 

12/01/2011 
09/08/2017 

09/08/2017 
09/01/2016 

03/01/2017 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
09/08/2017 

09/08/2017 
09/01/2016 

03/01/2017 
100   

 


Begin Construction Phase

End Construction Phase
04/01/2012 

09/01/2012 
08/30/2018 

03/09/2020 
08/01/2018 

12/01/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2012 

06/01/2012 
03/09/2020 

03/09/2020 
01/06/2020 

03/20/2020 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3 0

Bond Funding Cost
Adopted:
$1,000,000
Current Approved:
$785,000
Actual Expenditures:
$785,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31