Operations and Maintenance Center |
Description: Purchase of land and development of a operations/maintenance center for the City of Lompoc Transit.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Santa Barbara |
City | Lompoc |
Zip Code | 93438 |
Senate District |
19 |
Assembly District | 33 |
Congressional District | |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
RICHARD FERNBAUGH | (805) 875-8268 | R_FERNBAUGH@CI.LOMPOC.CA.US |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $41 | $41 | ||||
PTMISEA-99313 |
$2,105 | $0 | $2,105 | ||||
PTMISEA-99314 |
$62 | $0 | $62 | ||||
Non-bond Funding | |||||||
Total**** | $2,167 | $41 | $2,209 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$110 | $147 | $257 | $656 | $656 | $-399 | |
Right of Way |
$156 | $-147 | $9 | $604 | $604 | $-595 | |
Construction |
$1,901 | $41 | $1,942 | $0 | $0 | $1,942 | |
Total* | $2,167 | $41 | $2,209 | $1,260 | $1,260 | $948 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/01/2013 02/28/2014 |
07/01/2015 05/04/2018 |
01/02/2014 03/31/2018 |
98 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/30/2015 12/30/2015 |
11/02/2021 11/02/2021 |
06/30/2021 12/31/2022 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/01/2016 03/30/2016 |
10/08/2018 10/08/2018 |
01/01/2023 03/01/2023 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31