Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Purchase and remodel transit facility |
Description: Purchase and remodel a transit facility
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Tehama |
City | Gerber, Ca |
Zip Code | 96035 |
Senate District |
04 |
Assembly District | 02 |
Congressional District | 02 |
Caltrans District |
02 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 30 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
BARBARA O'KEEFFE | (530) 385-1462 | BOKEEFFE@TCPW.CA.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $40 | $40 | ||||
PTMISEA-99313 |
$1,514 | $32 | $1,546 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $198 | $198 | ||||
Local** |
$0 | $90 | $90 | ||||
Total**** | $1,514 | $360 | $1,873 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$50 | $0 | $50 | $180 | $180 | $-130 | |
Right of Way |
$0 | $0 | $0 | $1,143 | $1,143 | $-1,143 | |
Construction |
$1,464 | $360 | $1,823 | $550 | $550 | $1,274 | |
Total* | $1,514 | $360 | $1,873 | $1,873 | $1,873 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
12/17/2013 12/17/2013 |
02/01/2013 07/01/2013 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2012 12/01/2012 |
12/17/2013 12/17/2013 |
11/01/2013 06/30/2014 |
5 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2013 03/01/2014 |
02/26/2020 02/26/2020 |
09/30/2019 02/20/2020 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
02/01/2014 05/01/2014 |
02/26/2020 02/26/2020 |
02/20/2020 06/30/2020 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 30 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,513,699 |
Current Approved: |
$1,545,873 |
Actual Expenditures: |
$1,545,873 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31