Purchase and remodel transit facility

Description: Purchase and remodel a transit facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tehama
City Gerber, Ca
Zip Code 96035
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    30  
Reduced Operating/Maintenance Cost  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BARBARA O'KEEFFE (530) 385-1462   BOKEEFFE@TCPW.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $40 $40
PTMISEA-99313
$1,514 $32 $1,546
Non-bond Funding
State/Federal*
$0 $198 $198
Local**
$0 $90 $90
 
Total**** $1,514 $360 $1,873

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$50 $0 $50 $180 $180 $-130
Right of Way
$0 $0 $0 $1,143 $1,143 $-1,143
Construction
$1,464 $360 $1,823 $550 $550 $1,274
 
Total* $1,514 $360 $1,873 $1,873 $1,873 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
12/17/2013 

12/17/2013 
02/01/2013 

07/01/2013 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2012 

12/01/2012 
12/17/2013 

12/17/2013 
11/01/2013 

06/30/2014 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2013 

03/01/2014 
02/26/2020 

02/26/2020 
09/30/2019 

02/20/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2014 

05/01/2014 
02/26/2020 

02/26/2020 
02/20/2020 

06/30/2020 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 30
Reduced Operating/Maintenance Cost 5 5

Bond Funding Cost
Adopted:
$1,513,699
Current Approved:
$1,545,873
Actual Expenditures:
$1,545,873

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31