New Facility Plan, Design, Land Purchase, and Construction

Description: Planning, land purchase, design, engineering, and construction of a new Maintenance and Operations facility for Gold Coast Transit.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City Oxnard
Zip Code 93030
 
Senate District
19, 23
Assembly District 35, 37, 41
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  60    10  
Increased Ridership  50    5  
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
HELENE BUCHMAN (805) 483-3959   HBUCHMAN@GOLDCOASTTRANSIT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $47 $47
PTMISEA-99313
$0 $9,681 $9,681
PTMISEA-99314
$824 $363 $1,187
Non-bond Funding
State/Federal*
$15,000 $-15,000 $0
Local**
$2,997 $-2,997 $0
 
Total**** $18,821 $-7,906 $10,915

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$2,000 $-2,000 $0 $0 $0 $0
Design(PS&E)
$2,000 $-756 $1,244 $890 $890 $354
Right of Way
$9,641 $-8,041 $1,600 $1,814 $1,814 $-214
Construction
$5,180 $2,891 $8,071 $8,211 $8,211 $-140
 
Total* $18,821 $-7,906 $10,915 $10,915 $10,915 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2012 

12/01/2012 
07/31/2014 

07/31/2014 
07/01/2013 

06/01/2014 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2012 

07/01/2012 
07/31/2014 

04/06/2017 
07/01/2014 

09/30/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2013 

07/01/2014 
03/20/2019 

03/20/2019 
04/01/2017 

06/30/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2015 

04/01/2015 
11/23/2020 

11/23/2020 
05/01/2020 

07/01/2020 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 60 10
Increased Ridership 50 5
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$824,289
Current Approved:
$10,868,130
Actual Expenditures:
$10,868,130

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31