Caltrans Logo

Bus Stops & Bus Shelters

Description: Construct additional bus shelters, benches and other accessories for the Amador Transit System

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Amador
City Jackson
Zip Code 95642
 
Senate District
01
Assembly District 10
Congressional District 03
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CARLA MEYER (209) 267-2282   CARLA@AMADORTRANSIT.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$34 $0 $34
PTMISEA-99314
$3 $0 $3
Non-bond Funding
 
Total**** $37 $0 $37

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$37 $0 $37 $37 $37 $0
 
Total* $37 $0 $37 $37 $37 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2011 

07/30/2011 
 

 
07/01/2011 

07/30/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2011 

08/30/2011 
 

 
08/01/2011 

08/30/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2011 

09/30/2011 
10/04/2012 

10/04/2012 
06/01/2012 

12/31/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2011 

11/01/2011 
04/19/2016 

04/19/2016 
02/01/2016 

02/15/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 5

Bond Funding Cost
Adopted:
$37,000
Current Approved:
$36,967
Actual Expenditures:
$36,967

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31