Bus Stop Signage (Up to 50 bus stops)

Description: Install signage and scheduling information at up to 50 Amador Transit bus stops

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Amador
City Jackson
Zip Code 95642
 
Senate District
01
Assembly District 10
Congressional District 03
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  3      
Increased Ridership  2      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CARLA MEYER (209) 267-9395   CARLA@AMADORTRANSIT.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$1 $-0 $1
PTMISEA-99314
$0 $0 $0
Non-bond Funding
 
Total**** $2 $-0 $1

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2 $-0 $1 $1 $1 $0
 
Total* $2 $-0 $1 $1 $1 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2011 

07/30/2011 
 

 
07/01/2011 

07/30/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2011 

08/30/2011 
 

 
08/01/2011 

08/30/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2011 

09/30/2011 
09/27/2013 

09/27/2013 
01/01/2012 

09/20/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2011 

11/30/2011 
09/27/2013 

09/27/2013 
08/01/2014 

08/23/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 3
Increased Ridership 2

Bond Funding Cost
Adopted:
$1,600
Current Approved:
$1,312
Actual Expenditures:
$1,312

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31