Bus Barn Construction Phase I

Description: Construct a bus barn to park the transit vehicles in a garage.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Glenn
City Willows
Zip Code 95988
 
Senate District
04
Assembly District 03
Congressional District 01, 03
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    8  
Reduced Operating/Maintenance Cost  15    12  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOHN LINHART (530) 934-6530   JLINHART@COUNTYOFGLENN.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$1 $9 $9
PTMISEA-99313
$467 $7 $473
Non-bond Funding
State/Federal*
$10 $32 $42
Local**
$0 $44 $44
 
Total**** $477 $91 $568

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $26 $26 $-26
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$477 $91 $568 $542 $542 $26
 
Total* $477 $91 $568 $568 $568 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2012 

02/01/2013 
08/20/2014 

08/26/2015 
10/01/2014 

04/30/2016 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2013 

05/01/2013 
03/05/2015 

03/21/2017 
05/01/2015 

10/01/2016 
16   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/15/2013 

09/01/2013 
03/21/2017 

04/11/2018 
04/01/2017 

04/30/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2013 

11/01/2013 
04/11/2018 

04/11/2018 
05/01/2018 

05/30/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 8
Reduced Operating/Maintenance Cost 15 12

Bond Funding Cost
Adopted:
$467,181
Current Approved:
$473,364
Actual Expenditures:
$473,364

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31