Garage Enhancement, Vehicle Purchase, Improve Transfer Station

Description: Purchase bus lift with accessories, brake lathe and required tools, transit administration vehicle and intall security cameras at transfer station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Taft
Zip Code 93268
 
Senate District
22
Assembly District 18
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  10    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TERESA BINKLEY (661) 763-1350   TERESA BINKLEY
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$18 $0 $18
PTMISEA-99314
$81 $-70 $11
Non-bond Funding
 
Total**** $99 $-70 $29

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$99 $-70 $29 $29 $29 $0
 
Total* $99 $-70 $29 $29 $29 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/15/2011 

09/01/2012 
 

 
08/15/2011 

09/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2013 

06/30/2013 
07/02/2014 

07/17/2019 
01/31/2015 

12/17/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 10 2

Bond Funding Cost
Adopted:
$98,588
Current Approved:
$28,588
Actual Expenditures:
$28,588

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31