Caltrans Logo

Rocklin Multi-Modal Station Park n ride lot expansion

Description: purchase property at multimodal station for additional parking lot install center barriers at 5 at grade crossings and protective fencing along UP railroad tracks

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
04
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  20      
Reduced Operating/Maintenance Cost      3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVID MELKO (530) 823-4030   DMELKO@PCTPA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$1,003 $-557 $446
Non-bond Funding
 
Total**** $1,003 $-557 $446

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,003 $-557 $446 $446 $446 $0
 
Total* $1,003 $-557 $446 $446 $446 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/30/2012 

03/30/2013 
11/04/2013 

11/04/2013 
11/30/2012 

03/30/2013 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/30/2012 

05/30/2013 
11/04/2013 

11/04/2013 
02/28/2012 

05/30/2013 
 

 


Begin Right of Way Phase

End Right of Way Phase
12/10/2012 

04/01/2013 
11/04/2013 

11/04/2013 
01/01/2013 

04/01/2013 
 

 


Begin Construction Phase

End Construction Phase
06/30/2013 

07/30/2014 
07/30/2014 

07/30/2014 
07/25/2013 

08/16/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
08/15/2014 

09/15/2014 
07/30/2014 

07/30/2014 
08/16/2013 

10/30/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 20
Reduced Operating/Maintenance Cost 3

Bond Funding Cost
Adopted:
$1,003,406
Current Approved:
$446,309
Actual Expenditures:
$446,309

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31