Bus Stop Improvements

Description: Design and construct improvements to various locations within Tuolumne County Transit service area

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tuolumne
City Sonora
Zip Code 95370
 
Senate District
14
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DIANE BYNUM (209) 533-5539   DBYNUM@CO.TUOLUMNE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $43 $43
PTMISEA-99313
$2,083 $0 $2,083
Non-bond Funding
State/Federal*
$0 $3,744 $3,744
Local**
$0 $6,471 $6,471
 
Total**** $2,083 $10,258 $12,341

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$164 $0 $164 $164 $164 $0
Right of Way
$72 $0 $72 $72 $72 $0
Construction
$1,846 $10,258 $12,105 $2,492 $2,492 $9,612
 
Total* $2,083 $10,258 $12,341 $2,729 $2,729 $9,612

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2012 

10/01/2013 
08/14/2014 

02/06/2015 
09/01/2014 

01/01/2016 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2012 

10/01/2013 
08/14/2014 

08/14/2014 
09/01/2014 

07/01/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
11/01/2013 

11/01/2013 
08/14/2014 

08/14/2014 
07/01/2016 

06/30/2017 
100   

 


Begin Construction Phase

End Construction Phase
01/01/2014 

12/01/2014 
08/03/2020 

07/31/2023 
04/01/2021 

10/15/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2015 

06/01/2015 
07/31/2023 

07/31/2023 
10/31/2023 

12/01/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10

Bond Funding Cost
Adopted:
$2,082,876
Current Approved:
$2,082,876
Actual Expenditures:
$2,082,876

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31